Kingstone retaining wall construction provider in Colorado

Kingstone retaining wall building tricks: Why you should backfill with stone? Versa-Lok recommends compacting the angular stone as you backfill, but check the installation instructions for the type of block you’re using. Backfill about 8 to 10 inches below the top of the capstones. This will allow enough room for the topsoil and turf. Secure the capstones with a specialty landscape block adhesive, which stays flexible over time. Make sure the blocks are dry before applying the adhesive. Overhang the capstones about 1 to 1-1/2 inch. Joe and Jake use a scrap 2×4 as a guide.

If the block Retaining wall is more substantial as in a metre high or more then the fence would have to be behind the wall instead of through or on top. Most Segmental Retaining Wall blocks do not have a big enough cavity or void for the fence post to be directly concreted inside them and would lack the strength to hold the weight of a fence. Generally, most walls are built using an aggregate (Gravel) backfill or in some circumstances No Fines Concrete (NFC). Because of this, an allowance has to be made for the fence post at the early construction stage such as installing PVC Piping as a sleave for the fence post to fit into, this would require some forethought and good planning.

We also repair existing retaining walls. Many railroad tie walls or older concrete retaining walls which may or may not include rocks or boulders are beginning to show signs of failure. Often times a homeowner will build a DIY retaining wall that needs help after years of service. We serve all of Colorado out of our home office in Colorado Springs. Please feel free to reach out to us with any questions you may have. Estimates are always free and everything we touch comes with a warranty. See even more info on Building and repair of retaining walls Colorado.

Spacers are set to maintain spacing and support the form prior to the pour. Wire ties snug the form and resist the pressure of the wet concrete. Wales align the form and brace the studs in forms more than 4 or 5 feet high. Two horizontal walls are sufficient for most forms, but they should not be spaced greater than 30 inches on center. For lower, lighter walls, it is possible to cast the wall at the same time you cast the footer. Larger walls always require separate pours for the footer and wall.

DON’T lay blocks on an unlevel surface. The first course (or row of blocks) sets the stage for the rest of the wall, so it’s vital that you make it perfectly level. If it isn’t, subsequent rows won’t be level either, resulting in a retaining wall that’s lopsided and unattractive. Use a four-foot carpenter’s level to ensure that the gravel layer below the first course of blocks is level before you start setting the blocks. Any discrepancies here will show up higher in the wall. DO stack blocks at a slight backward slope.